Home > Benefits > Fast Construction THERMOMASS.com System Benefits - Fast Construction  
Other THERMOMASS Benefits
Energy Efficiency
Durability
Design Flexibility
Environmentally Responsible
Return on Investment
Health and Safety
 
Quick Index
What is THERMOMASS?
About our company
Back to the Homepage
Complete Site Index
 
Contact Us
By telephone: (800) 232-1748
By fax: (515) 433-6088
By mail:
Composite Technologies Corporation
1000 Technology Drive
PO Box 950
Boone, Iowa 50036
By email
View the directory

Business owners know that time is money. The faster your building is operational, the sooner your bottom line improves. THERMOMASS understands this.

Insulated concrete sandwich wall facilities are among the fastest to construct. Tilt-up and precast concrete buildings have been built in as little as half the time of standard block-and-brick structures.

Since the insulation is integral to the wall system, extra insulating workers are not required. The walls are placed quickly meaning other trades can get to work sooner.

Here is an example of efficient construction using the THERMOMASS Building Insulation System.

Realizing the benefits of insulated concrete construction, SiteCast Construction built this 52,000 SF school in Ontario in only 25 weeks!

March
   
Project Starts
 

Construction started on March 1st, 1999. Foundations, foundation insulation, weeping tile and underground electrical and plumbing services were all installed in March.

April
   
Tilt Panels
 

Floor slab cast to a "super flat" finish. Fabrication of tilt-up panels commenced. Site services proceeded with installation of water main.

May
   
Panels Lifted
 

Panel fabrication continued. Panel lift started, and the next day structural steel installation commenced. Within 2 weeks the building structure was erected, with structural steel right behind. Mechanical and electrical trades commenced work.

June
   
Shell Completed
 

Completion of steel roof deck allowed roofing to commence. Sealing of the building proceeded with the installation of window frames and glazing. Electrical, mechanical, ductwork and sprinkler trades made rapid progress.

July
   
Interior Work
 

Electrical and mechanical rough-ins were completed. Work started on the Interior finishings.

August
   
Project Completed
 

Completion of interior finishes. Occupancy by Board took place on August 16th.

Students and teachers were welcomed into their new facility on the first day of school, August 30th, 1999.

Learn more about this school in our project profile.


 